Midterms Test Anthropic’s Political Outlook
- •U.S. midterms put Anthropic’s IPO plans and political support for rapid AI expansion under scrutiny
- •Anthropic’s Texas data center commitments include $50 billion with Fluidstack, $35 billion with Lambda and $9.1 billion with Riot Platforms
- •Texas permitting limits, New York’s up-to-one-year pause and possible congressional hearings shape policy risks for AI labs
Anthropic PBC faced a political test on Nov. 3, 2026, as U.S. midterm elections could change support for rapid AI development while the company pursues an initial public offering. Democrats skeptical of AI could win one or both congressional chambers and key governor’s races, increasing pressure on AI labs, especially over rapid data center construction. Republicans have generally aligned more closely with President Trump’s support for the technology.
The election outcome was not expected to change much before Anthropic’s IPO pricing and the start of trading. But Anthropic is seeking to raise at least as much as SpaceX’s record $86.2-billion debut, while AI-related stocks had fallen in recent weeks; a shift in political leadership could alter expectations about Anthropic’s ability to navigate policy.
Texas is central to the company’s data center plans. Gov. Greg Abbott ordered permits for new data centers withheld until an audit of power-grid risks is complete, saying “Texans come first.” Democratic nominee Gina Hinojosa called the move an “election year stunt.” Anthropic has a $50-billion partnership with Fluidstack for facilities in Texas and New York, its first major data center build-out undertaken directly. It also has a $35-billion pact with Lambda for a Nueces County data center and a $9.1-billion agreement with Riot Platforms for a Rockdale campus. Separately, banks are delaying plans to sell part of a $15-billion loan for a Nexus Data Centers project, Bloomberg News reported.
Bloomberg Intelligence litigation analyst Justin Teresi said the Texas governor would set the tone for policy affecting growth. He does not expect policy to return to its previous status quo, even if the current permitting pause ends; local governments could gain more power to block data centers. In New York, Gov. Kathy Hochul leads Republican challenger Bruce Blakeman in polls, and her July executive order pausing for up to one year large data centers that consume 50 megawatts or more is therefore likely to remain in place.
Anthropic and its partners may need to explain community benefits to state officials. Meta has promised 500 full-time jobs by 2035 for its Hyperion data center in Louisiana. Teresi said some states, including Louisiana, are responding to benefits such as education funding. Congressional hearings could also question executives about AI agents, including incidents involving a false murder report, and concerns that AI could wipe out humanity.
Technology companies have hired lawyers and lobbyists ahead of possible hearings. Anthropic has drawn more scrutiny from the Trump administration because it advocates AI safety and a coordinated slowdown in the most advanced models. JPMorgan Chase analysts said in a Monday client note that a Democratic takeover could raise fears of tighter regulation and an AI selloff, but said policy would be difficult to enact if Trump vetoes bills limiting AI expansion and Democrats lack veto-proof majorities in both chambers.